DSCN6331DSCN6332
The new sign on the south entrance,  it is pre-cast concrete. 
The sign came in three large pieces.

DSCN6319DSCN6328DSCN6320
To provide air conditioning to the new school building chilled water is
piped from the chiller plant north of the steam plant.  These pipes are six inches
in diameter  and will be buried about 4 feet underground.   
DSCN6365DSCN6366DSCN6367
The south entrance of the Gottlieb School:
new stairs leading the door (left), ramp up to the door (center and right).
DSCN6385DSCN6383DSCN6382
Auditorium ceiling
DSCN6402




   Student Lockers in high school commons area.




DSCN6424

Glass wall on east of media center leading out to patio.
DSCN6423


DSCN6414DSCN6413DSCN6412
Corridor walls have a wainscoting with a maple chair rail.  

Monday, August 1, 2011


DSCN6311
Air handling unit for science lab unit provides
cooling and heating and fresh air for lab 

DSCN6288
Main Mechanical room  has five pumps,  
three for cooling system two for the heating system 
                                                                                            DSCN6141DSCN6289
Typical piping above corridor ceiling:
Air ducts, electrical conduit, control wiring, heating and cooling equipment.

DSCN6291




Ceiling area above a circular seating area in the elementary commons area.











DSCN6307DSCN6308
Middle School hallway